Table of Contents
2.......... Project Information
2.3 Construction Programme and
Activities
2.5 Status of Environmental Licences,
Notification and Permits
3.......... Environmental Monitoring
Requirements
3.1 Construction Dust Monitoring
3.2 Construction Noise Monitoring
4.......... Implementation
Status of Environmental Mitigation Measures
5.......... Monitoring
Results
5.1 Construction Dust Monitoring
5.2 Regular Construction Noise
Monitoring
6.......... ENVIRONMENTAL
SITE INSPECTION AND AUDIT
6.2 Summary of Monitoring Exceedances
6.3 Summary of Environmental
Non-Compliance
6.4 Summary of Environmental Complaints
6.5 Summary of Environmental Summon and
Successful Prosecutions
7.1 Construction Programme for the Next
Three Month
7.2 Key Issues for the Coming Month
7.3 Monitoring Schedule for the Coming
Month
8.......... ConclusionS AND
RECOMMENDATIONS
List of Tables
Table
2.1........... Construction Activities in the
reporting month
Table
2.2........... Contact
Information of Key Personnel
Table
2.3........... Status
of Environmental Licenses, Notifications and Permits
Table
3.1 ......... Air Quality Monitoring Equipment
Table
3.2 ......... Location of Construction Dust Monitoring Station
Table
3.3 ......... Noise Monitoring
Parameters, Frequency and Duration
Table
3.4 ......... Noise Monitoring Equipment for Regular Noise
Monitoring
Table
3.5 ......... Noise Monitoring Stations
during Construction Phase
Table
3.6 ......... Noise Monitoring
Parameters, Frequency and Duration
Table
4.1........... Status of Required Submission under
Environmental Permit
Table
5.1 ......... Summary of 24-hour TSP
Monitoring Result in the Reporting Period
Table
5.2 ......... Summary of 1-hour TSP
Monitoring Result in the Reporting Period
Table
5.3 ......... Summary of Construction
Noise Monitoring Results in the Reporting Period
Table
6.1 ......... Observations and
Recommendations of Site Audit
Table
7.1........... Construction Activities in the
coming three month
List of Figures
Site Layout Plan |
|
Location of Air Quality Monitoring Station |
|
Locations of Noise Monitoring Station |
List
of Appendices
Construction Programme |
|
Project Organization Structure |
|
Implementation Schedule of Environmental Mitigation Measures |
|
Summary of Action and Limit Levels |
|
Calibration Certificates of Equipment |
|
EM&A Monitoring Schedules |
|
Air Quality Monitoring Results and their Graphical Presentations |
|
Noise Monitoring Results and their Graphical Presentations |
|
Event and Action Plan |
|
Cumulative Statistics on Complaints, Notification of Summons and
Successful Prosecutions |
|
Monthly Summary Waste Flow Table |
Central Kowloon Route
– Kai Tak West (CKR-KTW; Contract No. HY/2014/07) (hereafter called “the
Project”) covers part of the construction of the Central Kowloon Route (CKR).
The Project comprises
the follow works:
·
50x30m
access shaft with noise enclosure at Ma Tau Kok
(MTK);
·
100m long
cut-and-cover (C&C) tunnel at MTK;
·
Demolition
and re-provisioning of MTK Public Pier;
·
160m long
underwater tunnel (UWT) (Stage 1);
·
210m long
UWT (Stage 2);
·
60m long
C&C tunnel at Kai Tak;
·
130m long
depressed road and 200m long underpass at Kai Tak;
·
390m long
underground tunnel ventilation adit at Kai Tak;
·
Seawall
demolition and construction of new landing steps; and
·
Barging
Point enclosure and conveyor system.
The EM&A programme commenced on 4 April 2018.The impact EM&A for the Project includes
air quality and noise monitoring.
This is the
twenty-third monthly EM&A Report presenting the EM&A works carried out
during the period between 1 and 29 February 2020. As informed by the Contractor, major activities in the
reporting period were:
Locations |
Site Activities |
Kai Tak |
·
Excavation and ELS installation at cut & cover tunnel,
depressed road and underpass; ·
Construction of New Right of Way; ·
Temporary Grouting |
Ma Tau Kok |
·
TTM implementation; ·
Pipe piling works for cut and cover tunnel; ·
Rock Excavation; ·
ELS installation & Access platform concreting works; ·
Existing drainage diversion works; ·
Excavation at Covered Walkway |
Kowloon Bay |
·
Excavation for Stage 1 underwater tunnel; ·
Dewatering well and observation well installation; ·
S1 Truss fabrication and installation; ·
Temporary Grouting; ·
Pumping Test |
Barging Point |
·
Barging point operation (Spoil Disposal) |
Breaches of Action and Limit Levels for Air Quality
All 24-hour TSP result was below the Action
and Limit Levels at all monitoring locations in the reporting month.
All 1-hour TSP result was below the Action and
Limit Levels at all monitoring locations in the reporting month.
Breaches of Action and Limit Levels for Noise
Regular Noise Monitoring
One (1) noise and air related complaint was received in the reporting month. Based on the investigation result, the noise nuisance from the construction site was minimized with the proper implementation of mitigation measures. Therefore, one action level of construction noise was triggered, and the investigation report was finalized on 18 February 2020.
No
exceedance of Limit Level of noise was recorded in the reporting month.
Complaint, Notification of Summons and Successful Prosecution
Two (2) complaints ((i) one complaint received by Highway Department on 6 February 2020 and (ii) one complaint received by Gammon Construction Limited on 8 and 10 February 2020 which were considered as the same case) were referred by the Contractor on 7 and 14 February 2020, both investigation reports were finalized on 18 February 2020.
Reporting Changes
There was no
reporting change in the reporting month.
Future Key Issues
Key issues to be
considered in the next three months included:
Locations |
Site Activities |
Kai Tak |
·
Base slab and wall construction at underpass and depressed
road; ·
Excavation and ELS installation at cut & cover tunnel,
depressed road and underpass; ·
Temporary Grouting; ·
Backfilling works and ELS removal at Underpass |
Ma Tau Kok |
·
TTM implementation; ·
Rock excavation; ·
ELS installation and Access platform concreting works; ·
Pipe piling works for cut and cover tunnel; ·
Laying of lighting ducts at Metered Carpark area; ·
Fresh water pipe installation works; ·
Covered walkway construction |
Kowloon Bay |
·
Excavation for stage 1 underwater tunnel; ·
ELS installation; ·
Temporary Grouting; ·
Pumping Test |
Barging Point |
·
Barging point operation (Spoil Disposal) |
·
Section 1:
Introduction
·
Section 2:
Project Information
·
Section 3:
Environmental Monitoring Requirement
·
Section 4:
Implementation Status of Environmental Mitigation Measures
·
Section 5:
Monitoring Results
·
Section 6:
Environmental Site Inspection and Audit
·
Section 7: Environmental Non-conformance
·
Section 8:
Future Key Issues
·
Section 9:
Conclusions and Recommendations
(a) construction of approximately 160m long cut-and-cover tunnel and
370m long underwater tunnel between the tunnel section at Ma Tau Kok and the depressed road of the CKR within Kai Tak
Development;
(b) reconstruction of the seawall at Ma Tau Kok
public pier, and the sloping seawall at the Former Kai Tak Airport Runway;
(c) construction of approximately 125m long depressed road and 200m
long underpass of the CKR within Kai Tak Development;
(d) construction of approximately 360m long underground tunnel
ventilation adit of the CKR;
(e) reconstruction of Kowloon City Ferry Pier Public Transport
Interchange; and
(f) other associated works.
Table 2.1 Construction Activities in the reporting month
Locations |
Site Activities |
Kai
Tak |
·
Excavation and ELS installation at cut & cover tunnel,
depressed road and underpass; ·
Construction of New Right of Way; ·
Temporary Grouting |
Ma
Tau Kok |
·
TTM implementation; ·
Pipe piling works for cut and cover tunnel; ·
Rock Excavation; ·
ELS installation & Access platform concreting works; ·
Existing drainage diversion works; ·
Excavation at Covered Walkway |
Kowloon
Bay |
·
Excavation for Stage 1 underwater tunnel; ·
Dewatering well and observation well installation; ·
S1 Truss fabrication and installation; ·
Temporary Grouting; ·
Pumping Test |
Barging
Point |
·
Barging point operation (Spoil Disposal) |
Table 2.2 Contact Information of Key Personnel
Party |
Role |
Position |
Name |
Telephone |
Fax |
Arup-Mott
MacDonald Joint Venture |
Residential
Engineer (ER) |
Engineer’s
Representative |
Mr. Jeffrey
Lau |
2268 3640 |
2268 3954 |
ERM |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker |
Ms. Mandy To |
2271 3313 |
2723 5660 |
Gammon |
Contractor |
Contracts Manager |
Mr. Alan Yan |
2516 8823 |
2516 6260 |
Environmental Manager |
Ms Michelle Tang |
9267 8866 |
|||
AECOM |
Contractor’s
Environmental Team (ET) |
ET Leader |
Mr. Y T Tang |
3922 9392 |
2317 7609 |
Table 2.3 Status of Environmental Licenses, Notifications and Permits
Permit / License No. / Notification/
Reference No. |
Valid Period |
Status |
Remarks |
|
From |
To |
|||
Further
Environmental Permit |
||||
FEP-01/457/2013/C |
28 Feb 2018 |
End of Project |
Valid |
-- |
Wastewater
Discharge License |
||||
WT00030290-2018 |
22 Mar 2018 |
31 May 2023 |
Valid |
Ma Tau Kok |
WT00030668-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Site Office at
Kai Tak West |
WT00030358-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Kai Tak West |
WT00030333-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Barging Point
at Portions 4B & 4C |
WT00030330-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Kowloon Bay |
Construction
Noise Permit |
||||
GW-RE0632-19 |
27 Aug 2019 |
26 Feb 2020 |
Valid |
Barging Point
Operation at Kai Tak Barging Point |
GW-RE1013-19 |
17 Dec 2019 |
16 Apr 2020 |
Valid |
Rock Breaking
at Ma Tau Kok |
GW-RE0986-19 |
6 Dec 2019 |
1 Jun 2020 |
Valid |
General Works
at Kai Tak |
GW-RE1012-19 |
17 Dec 2019 |
12 Jun 2020 |
Valid |
Welding and
backfilling at Stage 1 Underwater Tunnel |
Chemical Waste Producer Registration |
||||
5118-247-G2347-47 |
30 Jan 2018 |
End of Project |
Valid |
-- |
5118-247-G2347-48 |
30 Jan 2018 |
End of Project |
Valid |
-- |
Marine Dumping Permit |
||||
EP/MD/20-048 |
16 Oct 2019 |
15 Apr 2020 |
Valid |
Sediments requiring Type 1 - Open Sea Disposal |
EP/MD/20-092 |
3 Jan 2020 |
2 Feb 2020 |
Valid until 2 Feb 2020 |
Sediments requiring Type 1 (Dedicated Site) and Type 2 Confined
Marine Disposal |
EP/MD/20-122 |
6 Feb 2020 |
5 Mar 2020 |
Valid on 6 Feb 2020 |
Sediments requiring Type 1 (Dedicated Site) and Type 2 Confined
Marine Disposal |
Billing
Account for Construction Waste Disposal |
||||
7029909 |
22 Jan 2018 |
End of Project |
Account Active |
-- |
7031949 |
26 Feb 2020 |
26 May 2020 |
Account renew on 26
Feb 2020 |
Billing Account for Disposal of
Construction Waste (by vessels) |
Notification
Under Air Pollution Control (Construction Dust) Regulation |
||||
429442 |
5 Jan 2018 |
5 Jul 2025 |
Notified |
-- |
Monitoring Requirements
Monitoring Equipment
Table 3.1 Air Quality Monitoring Equipment
Tisch
Total Suspended Particulate Mass Flow Controlled High Volume Air Sampler |
|
Portable
direct reading dust meter |
Sibata Digital Dust Monitor |
Monitoring Locations
Table 3.2 Location of Construction Dust Monitoring Station
Location |
Monitoring Station |
Description |
E-A14a
[1] |
Block
B of Merit Industrial Centre |
Rooftop
(13/F) |
[1] The air monitoring station
proposed in the EM&A Manual (i.e. Wyler Gardens with ID: E-A14) was not
available for impact dust monitoring, therefore impact monitoring was conducted
at E-A14a as an alternative which was agreed by the ER, IEC and EPD.
Monitoring
Methodology
(a)
The HVS
was installed in the vicinity of the air sensitive receivers. The following criteria were considered in the
installation of the HVS as far as practicable: -
(i)
A horizontal platform with
appropriate support to secure the sampler against gusty wind was provided.
(ii)
Two samplers should
not be placed less than 2m apart from each other;
(iii)
The distance between the HVS and
any obstacles, such as buildings, was at least twice the height that the
obstacle protrudes above the HVS.
(iv)
A minimum of 2 meters separation
from walls, parapets and penthouse for rooftop sampler.
(v)
A minimum of 2 meters separation
from any supporting structure, measured horizontally is required.
(vi)
No furnace or incinerator flues
nearby.
(vii)
Airflow around the sampler was
unrestricted.
(viii)
The sampler was located more than
20 meters from any dripline.
(ix)
Any wire fence and gate, required
to protect the sampler, did not obstruct the monitoring process.
(x)
Permission was obtained to set up
the samplers and access to the monitoring station.
(xi)
A secured supply of electricity
was obtained to operate the sampler.
(b)
Preparation
of Filter Papers
(i)
Glass fibre filters, G810 were
labelled and sufficient filters that were clean and
without pinholes were selected.
(ii)
All filters were equilibrated in
the conditioning environment for 24 hours before weighing. The conditioning
environment temperature was around 25 °C and not variable by more than ±3 °C;
the relative humidity (RH) was < 50% and not variable by more than ±5%. A
convenient working RH was 40%.
(iii)
All filter papers were prepared
and analysed by ALS Technichem (HK) Pty Ltd., which is a HOKLAS accredited laboratory
and has comprehensive quality assurance and quality
control programmes.
(c)
Field
Monitoring
(i)
The power
supply was checked to ensure the HVS works properly.
(ii)
The filter holder and the area
surrounding the filter were cleaned.
(iii)
The filter holder was removed by
loosening the four bolts and a new filter, with stamped number upward, on a
supporting screen was aligned carefully.
(iv)
The filter was properly aligned
on the screen so that the gasket formed an airtight seal on the outer edges of
the filter.
(v)
The swing bolts were fastened to
hold the filter holder down to the frame.
The pressure applied was sufficient to avoid
air leakage at the edges.
(vi)
Then the shelter lid was closed
and was secured with the aluminium strip.
(vii)
The HVS was warmed-up for about 5
minutes to establish run-temperature conditions.
(viii)
A new flow rate record sheet was
set into the flow recorder.
(ix)
On site temperature and
atmospheric pressure readings were taken and the flow rate of the HVS was
checked and adjusted at around 1.3 m3/min, and
complied with the range specified in the EM&A Manual (i.e. 0.6-1.7 m3/min).
(x)
The programmable digital timer
was set for a sampling period of 24 hrs, and the starting time, weather
condition and the filter number were recorded.
(xi)
The initial elapsed time was
recorded.
(xii)
At the end of sampling, on site
temperature and atmospheric pressure readings were taken and the final flow
rate of the HVS was checked and recorded.
(xiii)
The final elapsed time was
recorded.
(xiv)
The sampled filter was removed
carefully and folded in half length so that only
surfaces with collected particulate matter were in contact.
(xv)
It was then placed in a clean
envelope and sealed.
(xvi)
All monitoring information was
recorded on a standard data sheet.
(xvii) Filters were then sent to ALS Technichem (HK) Pty Ltd. for analysis.
(d)
Maintenance
and Calibration
(i)
The HVS and its accessories were maintained in good working condition, such as
replacing motor brushes routinely and checking electrical wiring to ensure a
continuous power supply.
(ii)
HVSs were calibrated using
TE-5025A Calibration Kit upon installation and thereafter at bi-monthly
intervals.
(iii)
Calibration certificate of the TE-5025A Calibration Kit and the HVSs are provided in
Appendix E.
(a)
Measuring Procedures
The measuring procedures of the 1-hour dust
meter are in accordance with the Manufacturer’s Instruction Manual as follows:
(i)
Turn the power on.
(ii)
Close the air collecting opening cover.
(iii)
Push the “TIME SETTING” switch to [BG]
(iv)
Push “START/STOP”
switch to perform background measurement for 6 seconds.
(v)
Turn the knob at SENSI ADJ position to insert
the light scattering plate.
(vi)
Leave the equipment for 1 minute upon “SPAN
CHECK” is indicated in the display.
(vii)
Push “START/STOP” switch to perform automatic
sensitivity adjustment. This measurement takes 1 minute.
(viii)
Pull out the knob and return it to MEASURE
position.
(ix)
Push the “TIME SETTING” switch the time set
in the display to 3 hours.
(x)
Lower down the air collection opening cover.
(xi)
Push “START/STOP” switch to start
measurement.
(b)
Maintenance and
Calibration
(i)
The 1-hour TSP meter
was calibrated at 1-year intervals against a continuous particulate TEOM
Monitor, Series 1400ab. Calibration certificates of the Laser Dust Monitors are
provided in Appendix E.
Monitoring Schedule for the
Reporting Month
Monitoring Requirements
Table 3.3 Noise Monitoring Parameters, Frequency and Duration
Parameter and Duration |
Frequency |
30-mins
measurement at each monitoring station between 0700 and 1900 on normal
weekdays. Leq, L10 and L90
would be recorded. |
At least once per week |
Table 3.4 Noise Monitoring Equipment for Regular Noise Monitoring
B&K (Model No. 2238) |
|
Acoustic
Calibrator |
B&K (Model
No. 4231) |
Monitoring Locations
Table 3.5 Noise Monitoring Stations during Construction Phase
Location |
Monitoring Station |
Description |
Measurement |
E-N12a [1] |
19 Hing Yan Street |
Rooftop (9/F) |
Façade |
E-N21a [1] |
Block B of Merit Industrial Centre |
Rooftop (13/F) |
Free field [2] |
Notes:
[1] The noise monitoring stations proposed in
the EM&A Manual (i.e. Grand Waterfront Tower 3 with ID: E-N12 and Hang Chien Court Block J with ID: E-N21) were not available for
impact noise monitoring, therefore impact monitoring was conducted at E-N12a
and E-N21a as an alternative which was
agreed by the ER, IEC and EPD.
[2] A
correction of +3 dB(A) was made to the free field measurements.
Monitoring
Parameters, Frequency and Duration
Table 3.6 Noise Monitoring Parameters, Frequency and Duration
Location |
Parameter and Duration |
Frequency |
E-N12a and E-N21a |
30-mins measurement at each
monitoring station between 0700 and 1900 on normal weekdays. Leq, L10 and L90 would
be recorded. |
At
least once per week |
Monitoring Methodology
(a)
The sound level meter was set on
a tripod at a height of 1.2 m above the ground.
(b)
Façade measurement was made at
E-N12a.
(c)
Free field measurements was made at monitoring location E-N21a. A correction of +3
dB(A) shall be made to the free field measurements.
(d)
The battery condition was checked to ensure the correct
functioning of the meter.
(e)
Parameters such as frequency
weighting, the time weighting and the measurement time were set as follows:
(i)
frequency weighting: A
(ii)
time weighting: Fast
(iii)
time measurement: Leq(30-minutes) during non-restricted
hours i.e. 0700 – 1900 on normal weekdays.
(f)
Prior to and after each noise
measurement, the meter was calibrated using the acoustic calibrator for 94
dB(A) at 1000 Hz. If the difference in
the calibration level before and after measurement was more than 1 dB(A), the
measurement would be considered invalid and repeat of noise measurement would
be required after re-calibration or repair of the equipment.
(g)
During the monitoring period, the
Leq, L10 and L90
were recorded. In addition, site
conditions and noise sources were recorded on a standard record sheet.
(h)
Noise measurement was paused
during periods of high intrusive noise (e.g. dog barking, helicopter noise) if
possible. Observations were recorded when intrusive noise was unavoidable.
(i)
Noise monitoring was cancelled in
the presence of fog, rain, wind with a steady speed exceeding 5m/s, or wind
with gusts exceeding 10m/s.
(a)
The
microphone head of the sound level meter was cleaned with soft
cloth at regular intervals.
(b)
The meter
and calibrator were sent to the supplier or HOKLAS laboratory to check and
calibrate at yearly intervals.
(c)
Calibration
certificates of the sound level meters and acoustic calibrators are
provided in Appendix
E.
Monitoring Schedule for the Reporting Month
Table 4.1 Status of Required Submission under Environmental Permit
EP Condition |
Submission |
Submission
Date |
Condition 3.4 of |
Monthly EM&A Report
for January 2020 |
14 February 2020 |
Table 5.1 Summary of 24-hour
TSP Monitoring Result in the Reporting Period
ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
E-A14a |
45.2 |
16.6 – 65.4 |
197.3 |
260 |
Table 5.2 Summary of 1-hour TSP Monitoring Result in the Reporting Period
ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
E-A14a |
63.3 |
56.5 – 66.7 |
302.4 |
500 |
Table 5.3 Summary of Construction Noise Monitoring Results in the Reporting Period
ID |
Range, dB(A), Leq (30 mins) |
Limit Level, dB(A), Leq (30 mins) |
E-N12a |
65.3
– 67.1 |
75 |
E-N21a |
62.3
– 65.7 |
75 |
l Excavation profiles
must be properly designed and executed.
l Stockpiling site(s)
shall be lined with impermeable sheeting and bunded. Stockpiles shall be fully
covered by impermeable sheeting to reduce dust emission.
l Excavation and
stockpiling should be carried out during dry season as far as possible to
minimise potentially contaminated runoffs from the Concerned Soil.
l Regular site audit
will be conducted under the Environmental Monitoring and Audit (EM&A)
programme to ensure the soil excavation, stockpiling and backfilling works are
carried out in accordance with this report.
Findings of the site audit will be presented in Table 6.1.
l The truck
transferring Concerned Soil shall be covered entirely by impervious sheeting to
ensure that the dusty materials do not leak from the truck.
Table 6.1 Observations and Recommendations
of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Air
Quality |
Nil |
Nil |
Nil |
Noise |
5 February 2020 |
· Breaker’s head was
not wrapped with the acoustic mat during the breaking at Ma Tau Kok. The Contractor was reminded
to wrap the breaker’s head with acoustic mat to minimize the noise impact. |
The item was
rectified by the Contractor on 6 Feb 2020. |
12 February 2020 |
· Breaker’s head
was not wrapped properly with the acoustic mat to minimize the noise impact
at Ma Tau Kok. The Contractor was reminded to wrap
the breaker’s head before commencing breaking. |
The item was
rectified by the Contractor on 13 Feb 2020. |
|
Reminder: · The Contractor
was reminded to maintain the sound canvas properly on the generator at Ma Tau
Kok. |
The item was
rectified by the Contractor on 13 Feb 2020. |
||
26 February 2020 |
Reminder: |
The item was
rectified by the Contractor on 27 Feb 2020 |
|
Water
Quality |
5 February 2020 |
· Oil drums were observed stored without drip tray at Ma Tau Kok. The Contractor was reminded to provide a drip tray
for oil drums to prevent accidental spillage. |
The item was
rectified by the Contractor on 10 Feb 2020. |
12 February 2020 |
· Bunding at Landing Step Area was not erected properly
along the edge of site boundary. The Contractor was
reminded to improve the boundary to prevent muddy water seepage. |
The item was
rectified by the Contractor on 17 Feb 2020. |
|
19 February 2020 |
Reminder: · The Contractor was
reminded to seal the hole of drip tray at Ma Tau Kok
to maintain the oil interception . |
The item was
rectified by the Contractor on 21 Feb 2020. |
|
Reminder: ·
The Contractor was reminded to maintain the silt
curtain at Steel Platform. |
The item was
rectified by the Contractor on 21 Feb 2020. |
||
26 February 2020 |
Chemicals were observed stored without drip tray at the hopper barge
near Steel Platform. The Contractor was reminded to
provide proper measure for chemical storage to prevent accidental spillage. |
The item was
rectified by the Contractor on 28 Feb 2020. |
|
Waste/
Chemical Management |
Nil |
Nil |
Nil |
Land
Contamination |
Nil |
Nil |
Nil |
Landscape &
Visual |
Nil |
Nil |
Nil |
Permits/ Licenses |
Nil |
Nil |
Nil |
Table 7.1 Construction Activities in the coming three months
Locations |
Site Activities |
Kai
Tak |
·
Base slab and wall construction at underpass and depressed
road; ·
Excavation and ELS installation at cut & cover tunnel,
depressed road and underpass; ·
Temporary Grouting; ·
Backfilling works and ELS removal at Underpass |
Ma
Tau Kok |
·
TTM implementation; ·
Rock excavation; ·
ELS installation and Access platform concreting works; ·
Pipe piling works for cut and cover tunnel; ·
Laying of lighting ducts at Metered Carpark area; ·
Fresh water pipe installation works; ·
Covered walkway construction |
Kowloon
Bay |
·
Excavation for stage 1 underwater tunnel; ·
ELS installation; ·
Temporary Grouting; ·
Pumping Test |
Barging
Point |
·
Barging point operation (Spoil
Disposal) |